A.
No certificate of occupancy shall be issued until the required site improvements have
been completed in accordance with an approved simplified site plan or final site development
plan. When the occupancy of a structure is desired prior to the completion of the
required site improvements, a temporary certificate of occupancy may be issued only
if the owner or developer provides a form of surety satisfactory to the county attorney
in an amount equal to the costs of labor and materials plus ten percent (10%) contingency
allowance satisfactory to the zoning administrator.
B.
All required improvements shall be completed and approved within six (6) months or
the surety may be forfeited. (7-7-05; 7-19-18.)