§ 8-1011. Surety requirements.  


Latest version.
  • Surety in an amount equal to twenty-five percent (25%) of the cost of materials and installation of landscaping, screening and buffering materials, including fences, shall be provided in a form acceptable to the county attorney, prior to the issuance of a certificate of occupancy (CO) or final inspection to ensure the landscaping was installed properly and remains healthy. This surety shall be released at the end of two (2) years from the issuance of a final certificate of occupancy or final inspection date, if an inspection shows the landscaping remains healthy. All required landscaping shall be the responsibility of the property owner(s). All plants damaged by insects, disease, vehicular traffic, acts of God, or vandalism shall be replaced. (7-7-05; 4-21-16; 7-19-18.)